Ogle House Remodel

List of Items to be completed:

***** Please note. Drawings are not to scale and dimensions are close but not 100% accurate. Window and wall sizes will need to be verified by Contractor Tom Hall ***

**** ADA Toilet, Pedestal sink, Shower Base, Bath Tile, Shower/Sink Faucets, HVAC system, and Flooring (TBD) will be provided by Home owner. ***

  1. Remove all existing flooring up to, but not including, Hardwood floors in Bedroom 1, Bedroom 2, Dining Room, and Family Room.
  2. Remove Interior Walls separating Kitchen, Bath and Bedroom 3. (2 walls Total)
  3. Remove Base Cabinets and appliances in Kitchen, Laundry Room, Bath and Bedroom 3. (Kitchen Cabinets to be reinstalled after flooring)
  4. Remove Flooring and Subflooring in Kitchen, Laundry Room, Bath and Bedroom 3.
  5. Level Floor Joists using existing methods and Jacks as needed in Kitchen, Laundry Room, Bath and Bedroom 3
  6. Move any plumbing-piping - electrical for new layout
  7. Install new 3/4" plywood Subfloor in Kitchen, Laundry Room, Bath and Bedroom 3
  8. Erect walls and install shower base for Bath along with all plumbing rough-ins
  9. Install Bath Tile in Bath
  10. Install Flooring Hardwood style (TBD) in Kitchen, Laundry Room, and Bedroom 3  "Flooring between rooms needs to be as level as possible for easy Wheelchair access"
  11. Install bath fixtures and finish plumbing-wiring in Kitchen, Laundry Room, Bath and Bedroom 3
  12. Install Mini-Split Ductless HVAC system
  13. Replace 6 windows as noted
  14. Replace Front Entry Door
  15. Remove Door in Bedroom 2 and match interior and Exterior surrounding look.
  16. Create Attic and Below house access hatches in Bedroom 3 to match Current access.
  17. Create-install gate in front of steps on front porch.

 